OCP-1Z0-053-200题-113题-158

QUESTION 113

You create two resource plans, one for data warehouse loading jobs at night and the other for application jobs

at day time. You want the resource plans to activateautomatically so that the resource allocation is optimum

as desired by the activity.

How would you achieve this?

A. Implement job classes

B. Implement Scheduler windows

C. Implement the mapping rule for the consumer groups

D. Set the SWITCH_TIME resource plan directive for boththe resource plans

Answer: B

同158题:http://blog.csdn.net/rlhua/article/details/13094803


Explanation/Reference:

Section: Backup, Recovery & Recovery Manager (RMAN)

原文地址:https://www.cnblogs.com/hzcya1995/p/13316061.html